A visibility splay is the triangle of clear sight a driver needs when pulling out of an access onto a road, so they can see oncoming traffic in time to stop or wait. It’s drawn on a plan as two measurements, the x distance back from the road edge and the y distance along it, and everything inside that triangle has to stay free of obstructions.

Splays sound like a small drawing detail, but they decide where an access can go, how much land a scheme needs to control and which conditions get attached to a permission. Getting them right early saves redesigns later.

What are the x and y distances in a visibility splay?

The x distance is how far back from the edge of the carriageway the driver’s eye is assumed to be, measured along the centre of the access. The standard figure is 2.4 metres, which represents a driver sitting in a car with the front of the vehicle just short of the road.

Manual for Streets allows a shorter x distance of 2 metres in some very lightly trafficked, slow speed situations, accepting that the front of the car will nose slightly into the road. Highway authorities treat that as an exception, so it needs to be argued for.

The y distance is how far along the road the driver needs to see in each direction. It’s based on the stopping sight distance for the speed of traffic on that road. Under Manual for Streets, that works out at 43 metres for 30mph traffic and 25 metres for 20mph.

Which standard applies, Manual for Streets or DMRB?

The standard that applies depends on the road. Manual for Streets is used for most residential and lower speed streets. Faster roads, or roads where the highway authority asks for it, are assessed against the Design Manual for Roads and Bridges, which gives longer y distances.

Picking the right standard is often the first discussion with the highway authority, and it can make a big difference to the splay you need. Our article on Manual for Streets or DMRB explains how that choice gets made.

Is the y distance based on the speed limit?

The y distance should be based on the speed traffic actually travels at, which isn’t always the posted limit. On a road signed at 40mph where most drivers are doing 32mph, the measured speeds can support a shorter splay than the limit suggests.

That’s what a speed survey is for. Automatic traffic counters record vehicle speeds over a week or so, and the 85th percentile speed, adjusted for wet weather, is used to set the y distance. On a tight frontage, that survey can be the difference between an access that works and one that doesn’t.

Who needs to control the land inside a visibility splay?

The land inside a visibility splay needs to be either public highway or land the applicant controls. If a splay crosses a neighbour’s front garden or a third party verge, nobody can guarantee it will stay clear, and the highway authority is likely to object.

This is why splays should be drawn against an accurate topographical survey and the highway boundary before a layout is fixed. Finding out at application stage that the splay clips land you don’t own can mean moving the access, buying a strip of land or going back to the drawing board.

What planning conditions apply to visibility splays?

Planning permissions commonly include a condition requiring the splays to be provided before the access is used and kept clear of anything above a set height from then on. Low walls, hedges, fences, parked cars and signage can all breach that condition if they grow or get built into the triangle later.

For larger schemes, the access works may also sit within a Section 278 agreement with the highway authority. Our guide to Section 278 and Section 38 agreements covers how those agreements run.

Do driveways and pedestrian routes need splays too?

Driveways and pedestrian routes often need splays too, though they’re smaller. A private driveway onto a quiet residential street may need a vehicle splay plus pedestrian visibility splays, commonly 2 metres by 2 metres either side, so drivers reversing or pulling out can see people on the footway.

Requirements vary between highway authorities, so it’s worth checking the local design guide early, particularly on infill and small residential schemes where space is tight.

How do visibility splays fit into site access design?

Visibility splays sit alongside geometry, gradients and vehicle tracking as part of the overall access design. A splay might work on paper but fall apart once refuse vehicle tracking moves the access a few metres, so the pieces need to be checked together.

We cover the wider process in our pieces on how site access design shapes a planning application and on swept path analysis. Splays are also one of the things a road safety audit will look at closely.

Talk to TPA about your site access

If you’re weighing up a site and aren’t sure the access will work, a visibility check at the start can save months later on. TPA has offices in London, Bristol, Cambridge and Norwich, and our team can assess splays, commission speed surveys and agree the approach with the highway authority. Get in touch to talk through your scheme.