Project Description
CLIENT
London Luton Airport
SECTORS
Commercial
Port
LOCATION
London Luton Airport
PLANNING AUTHORITY
N/A
HIGHWAY AUTHORITY
N/A
PROJECT TEAM
Ryebridge Construction
PROJECT MANAGER
Andrew Snowden
PROJECT DIRECTOR
James Darrall

PROJECT
We were appointed by Ryebridge Construction on behalf of London Luton Airport (LLA) to undertake a number of Road Safety Audits for the proposed reconfiguration of its Mid-Term Car Park.
APPROACH
Works were proposed at the existing Mid-Term Car Park (MTCP) at Luton Airport to provide a one-way carriageway and footway around the perimeter of the existing car park, with reconfiguration of the car parking within the remainder of the site. This also provided a bus route with new bus stops and drop off points.
We carried out Road Safety Audits (RSA) at Stage 1 (Preliminary Design), Stage 2 (Detailed Design) and Stage 3 (Completion) of the design process. This included two Stage 3 RSAs; one pre-opening and one post-opening of the car park. All Road Safety Audits were carried out by our independent team of Road Safety Auditors, fully qualified in accordance with DMRB GG119.
Overall, the Stage 1 Audit raised six road safety issues. All issues and recommendations were accepted by the designer and the Stage 2 Audit subsequently raised only one road safety issue.
OUTCOME.
Following the completion of construction, the post-opening Stage 3 RSA found only minor road safety issues such as areas where patch resurfacing would be required or additional road markings.